Tech Tip #15
Load Control Strategy
The way the demand controller controls loads is called the load control
strategy. In one sentence, it is the definition of each load's importance
in relation to all other loads being controlled by the system.
The sequence in which loads are shed is critical. A good load control
strategy is the single most important factor that will
make or break a demand control application.
Many of the early demand controllers did not have built-in features for
changing or customizing the load control strategy, which led to poor control
and reduced comfort. Today's Energy Sentry controllers are a great improvement
over the old because of the flexibility provided by advanced microcomputer
technology. The user is able to program a customized load control
strategy that works best for the home's architecture, the heating and cooling
equipment, the loads under control, the electric use in the household, and
most of all, his or her lifestyle.
Generally, there are three load control strategies: priority (fixed),
rotating or combination.
Fixed Priority Strategy
Priority strategy sheds the least important loads first and the most
important last. The last load shed is the first to be restored. The priority
strategy has the advantage of keeping high-priority rooms (such as the family
room and dining room) at the desired temperature while low-priority areas
(such as the basement or utility room) are allowed to experience small temperatures
drops during peak demand periods.
Fixed Priority Strategy
Heat Pump/Air Conditioner Home
| Priority |
Shed Sequence |
Load |
Demand |
| 1 (Highest) |
Last Load Shed |
Dryer (Heating Element Only) |
5.5 KW |
| 2 |
7th |
Compressor #1 |
3.0 - 7.0 KW |
| 3 |
6th |
Compressor #2 |
3.0 - 7.0 KW |
| 4 |
5th |
Water Heater |
4.5 KW |
| 5 |
4th |
Strip Heat #1 (Electric Furnace) |
5.0 KW |
| 6 |
3rd |
Strip Heat #2 (Electric Furnace) |
5.0 KW |
| 7 |
2nd |
Strip Heat #3 (Electric Furnace) |
5.0 KW |
| 8 (Lowest) |
1st Load Shed |
Strip Heat #4 (Electric Furnace) |
5.0 KW |
| NOTES: |
Compressor is not shed when outside temperature is below 30°F (When
outside thermostat is installed.) Compressor cannot be restarted for at
least five minutes after it is shed. This delay is for compressor protection. |
When the rate of total power consumption is projected to exceed the demand
limit (dL) setting, the controller looks for the lowest priority load in
the assigned priority of all the loads that can be shed, and sheds it. If
necessary, more loads are shed in ascending priority order to keep the average
demand below the dL setting.
In controllers with eight relays, up to eight circuits are turned on
and off. Priority Level 1 has the highest priority last off, first
on. Priority Level 8 has the lowest priority first off, last on. The
on/off decision is made and carried out every minute. In controllers with
16 control points, Level 16 is the lowest priority.
In fixed priority strategy, load control can sometimes be enhanced by
assigning on-times or off-times of up to 20 minutes each to certain loads.
This is particularly useful for controlling heat pump and air conditioning
compressors, which require time-delay protection.
Rotate Strategy
The rotating sequence provides for an equal distribution of power to
all controlled loads. This may be desirable where all rooms are occupied
and require an equal share of power. Rotating strategy works best in electric
baseboard-heated homes where there is NO water heater and dryer to
control.
Rotation is particularly useful when you have several heating loads and
want to make sure no load stays off for too long at a time. Since the reduction
in demand is shared by several loads, the desired comfort level is maintained
throughout the home.
In controllers with eight relays, all eight circuits are assigned an
equal priority. Loads are turned off and on sequentially every minute, as
needed, to maintain demand below the limit. At the beginning of each one-minute
interval, the first load previously turned off is turned on. The controller's
microcomputer keeps track of which load has been off longest and will restore
it first when it is able. The microcomputer continues to shed or restore
loads as necessary to maintain the demand limit setting and provide all
loads with essentially equal operating time. This is the standard pattern.
Unlike with fixed priority strategy, minimum on and off times are usually
not required, but you may assign them if desired.
Combination Fixed/Rotate Strategy
Baseboard-Heated Home
Priority |
Shed Sequence |
Load |
Demand |
1 (Highest) |
Last Load Shed |
Dryer (Heating Element Only) |
5.5 KW |
2 |
2nd |
Water Heater |
4.5 KW |
3 (Lowest)* |
1st* |
Living Room Heat |
3.5 KW |
3 (Lowest)* |
1st* |
Basement Heat |
4.0 KW |
3 (Lowest)* |
1st* |
Entry Heat |
1.5 KW |
3 (Lowest)* |
1st* |
Bedroom Heat |
2.0 KW |
3 (Lowest)* |
1st* |
Bedroom Heat |
2.0 KW |
3 (Lowest)* |
1st* |
Family Room Heat |
3.0 KW |
| *NOTES: |
With the rotating Strategy, the shedding sequence begins with the load
that has been restored the longest. When all #3 priority loads are shed,
the #2 priority load is shed next. The #1 Priority load is shed last, if
necessary. |
Combination Load Strategies
This is the most versatile and powerful strategy because so many combinations
are possible. For example, groups of rotating loads can be programmed with
or without fixed priority loads. The sample shows one combination. This
combination is recommended for electric baseboard homes and has proven to
provide superior results in that application.
|